Weekly owner report
SampleProgress
Second-floor framing is complete. Roof trusses arrived Thursday and go up next week. Photos attached.
Money
Contract $957,000. Approved changes $12,400. Paid to date $402,000.
Time
Four working days behind the plan because of rain. The contractor's recovery plan is attached, and we agree with it.
Decisions we need from you
Storefront glass color by Friday. One change order for $3,150 is ready for you to review, with our recommendation.